| Project |
INFO |
Job details |
| Becca made curtain thingies and pillows |
| Date Started: |
1/6/04 |
| Cost: |
$200 Fabric |
| Date Finish |
1/8/04 |
|
   |
| Put
up an outer wall where garage door is |
| Date Started: |
1/16/04 |
| Cost: |
$400 |
| Date Finish |
1/23/04 |
| Workers |
Me, Jim |
| Est timWe |
12-15 hours |
|
|
|
|
setting up
|
|
|
|
framing
|
|
|
|
wall going up
|
|
|
- Jim helped with this project
- 1/16/04
- Removed Garage door frame
- Framed in wall
- Put up plywood
- apply tar paper
- put in door
- 1/23/04
- shingled
-
|
|
|
No shingles
|
|
|
|
About 40% done
|
|
|
|
Done
|
|
|
|
|
Removed two large window on studio and made into a
shingled wall |
| Date Started: |
1/24/04 |
| Cost: |
$150.00 |
| Date Finish |
1/24/04 |
| Workers |
me, Jim, Becca |
| Est time |
6 hours |
|
- Jim helped with this project too
- Removed two large windows
- framed it
- put up plywood and tar paper
- shingled it
-
|
|
|
removing window
|
|
|
|
removing window
|
|
|
|
removing window
|
|
|
|
removing window
|
|
|
|
windows gone
|
|
|
|
|
windows gone
|
|
|
|
wall up
|
|
|
|
shingles started
|
|
|
|
about done
|
|
|
|
hot guy
|
|
|
|
|
Removed two small windows and made into a shingled wall |
| Date Started: |
1/25/04 |
| Cost: |
$60.00 |
| Date Finish |
1/25/04 |
| Workers |
Me, Becca |
| Est time |
4 hours |
|
- Removed two small windows
- framed it
- Put up plywood and tar paper
- shingled it
|
|
|
windows out
|
|
|
|
here is the window
|
|
|
|
framing
|
|
|
|
tared and boarded
|
|
|
|
inside view
|
|
|
|
|
all done
|
|
|
|
|
garage door |
| Date Started: |
1/27/04 |
| Cost: |
0 |
| Date Finish |
1/27/04 |
| Workers |
Me, Becca, Wayne |
| Est. time |
3 hours |
|
- Disassembled garage door and parts
- Had to cut it up and took it to the dump
|
|
Wired
for speakers |
| Date Started: |
1/27/04 |
| Cost: |
0 |
| Date Finish |
1/27/04 |
| Workers |
Me, Becca, Wayne |
| Est. time |
3 hours |
|
- put in speaker wire for the studio
|
| Removed Carpet |
| Date Started: |
1/29/04 |
| Cost: |
0 |
| Date Finish |
1/29/04 |
| Workers |
Becca, |
|
          |
| Moved the wall |
| Date Started: |
1/30/04 |
| Cost: |
N/A |
| Date Finish |
1/30/04 |
| workers |
Me, Jim |
| Hours |
3 |
|
- We moved the wall that separated shop from the studio
- Had to take down all shelving on shop side
- move shop desks
- move wall
- mount it to the ceiling and floor (cement screws)
|
|
Finish up insulation and get ready to drywall |
| Date Started: |
1/30/04 |
| Cost: |
N/A |
| Date Finish |
1/30/04 |
| workers |
Me, Jim |
| Hours |
3 |
|
- Finished some insulation and cleaned up and moved things for dry
walling the next day.
|
| Paint The living room |
| Date Started: |
1/31/04 |
| Cost: |
$100 |
| Date Finish |
2/5/04 |
| workers |
Becca,Pam, Jen, Cindy |
|
     
      |
|
Dry walled the ceiling and part of the wall |
| Date Started: |
1/31/04 |
| Cost: |
$100 |
| Date Finish |
1/31/04 |
| workers |
Me, Jim, Wayne, Rick, Dave, United rental |
| Hours |
5 |
|
- Dry walled the ceiling. used an drywall holder made it much easier.
|
|
Dry walled, Framed changing room, put light
in changing room |
| Date Started: |
2/6/04 |
| Cost: |
$300 |
| Date Finish |
2/7/04 |
| workers |
Me, Jim |
| Hours |
8 |
|
- Hung some more drywall
- Framed the changing room
- framed it with 2x4s
- mounted to studs in wall and ceiling
- mounted to floor with cement screws
- framed in door and installed Jim shimmed it to death :)
- put in a light switch for the changing area.
|
| 2/6/04 |
2/7/04 |
Dry walled, Framed changing
room, put light in changing room |
| 2/19/04 |
2/19/04 |
Finished the last of putting up the last of the
drywall |
| 2/20/04 |
02/21/04 |
mud and tape part of the place |
| 2/23/04 |
02/23/04 |
Replaced toilet in upstairs bathroom |
| Mudded 3 layers in the studio |
| Date Started: |
3/1/04 |
| Cost: |
$200 |
| Date Finish |
3/31/04 |
| workers |
Me, Jim, becca |
| Hours |
LOTS |
|
   |
| put in a new pump and filter for pool |
| Date Started: |
3/14/04 |
| Cost: |
$886 |
| Date Finish |
3/14/04 |
| Workers |
Me, Becca |
|
- Removed old stuff

- cleaned old Cement pad and removed plants
- started piping and laying new filter and pump, we hard piped this time
   |
|
Installed AC into studio |
| Date Started: |
3/27/04 |
| Cost: |
$200 |
| Date Finish |
3/27/04 |
| workers |
Me, Jim, |
| Hours |
4 |
|
- cut a hole in wall
- mounted AC
- Build a bracket for outside
- Wired for the 208 AC unit (extended a wire from the heater since
both units will not be operating at the same time)
 |
|
Primer the drywall |
| Date Started: |
4/1/04 |
| Cost: |
$90 |
| workers |
Me, becca, Pammy |
| Hours |
4 |
|
|
|
Texture walls |
| Date Started: |
4/3/04 |
| Cost: |
$70 |
| workers |
Me, Wayne, Jen is the Loaf pincher |
| Hours |
4 |
|
|
|
Paint walls |
| Date Started: |
4/4/04 |
| Cost: |
$100 |
| workers |
Me, becca, Pammy |
| Hours |
4 |
|
|
| Installed lights in studio |
| Date Started: |
4/15/04 |
| Cost: |
$400 |
| workers |
Me, Pam |
|
    |
| Replaced Back Gate |
| Date Started: |
4/22/04 |
| Cost: |
$200 |
| workers |
Me |
|
   |
| Install French Doors in studio |
| Date Started: |
4/24/04 |
| Cost: |
$300 |
| workers |
Me, Jamie |
|
  |
| Bedroom Remodel |
| Date Started: |
5/5/05 |
| Cost: |
$? |
| workers |
Becca, Rick Pam |
| End Date |
5/8/05 |
|
This was a pleasant surprise I went to
Florida for business and came back to a room makeover...
            |
|
Built the Fence |
| Date Started: |
5/28/04 |
| Cost: |
$500 |
| workers |
Me, Becca, Wayne, Jen, Rick, Sammi |
| Hours |
30 |
|
- dug 14 post holes
- we broke a water line and had to fix that we ended up moving the
water pipe away from the fence
- set posts
- removed old fence boards to reuse
- put up the boards
       |
| Installed AC into party building |
| Date Started: |
June 2004 |
| Cost: |
$200 |
| workers |
Me, Rick, |
| Hours |
3 |
|
- Removed window and put in AC unit
 |
| remove hedges trim trees |
| Date Started: |
6/12/04 |
| Cost: |
$0 |
| workers |
Me, |
| Hours |
20 |
|
- removed about a 30 foot row of hedges
- trimmed a couple big trees
|
| Painted outside of the studio |
| Date Started: |
6/12/04 |
| Cost: |
$200 |
| workers |
Me, pam |
| Hours |
lots |
|
- painted primer the shingles on outside of studio
- Then painted with matching paint
|
| built the bridge over the dog area |
| Date Started: |
6/19/04 |
| Cost: |
$200 |
| workers |
Me, Jim |
| Hours |
lots |
|
- moved trampoline to dog area
- built bridge going across
- put sides on
After:
  |
|
updated pool |
| Date Started: |
aug-sept 04 |
| Cost: |
$800 |
| workers |
Me |
| Hours |
lots |
|
- added two new skimmers
- Added a new filter and pump
|
|
Cut down tree |
| Date Started: |
10/1/04 |
| Cost: |
$1000 |
| workers |
contractor |
| Hours |
5 |
|
- Removed dogwood tree above pool
- Trimmed trees up front extensively
- removed stumps, (for the 30 feet of hedges that were there)
Before
    
After
  
|
| Tonsils removed / HOLIDAYS |
|
Didn't get much done in December do to
holidays, surgery and recovery. |